Seattle Public Schools

Construction Begins on Seven Projects

Projects to replace the school buildings at Kimball Elementary School, James Baldwin Elementary School, and Viewlands Elementary School started this summer and will be complete in time for the 23-24 school year. Seismic improvements have begun for the east buildings at Lincoln High School.

Work began on the modernization and expansion project at West Seattle Elementary School. Classroom addition projects are also underway at Leschi Elementary School and Madison Middle School.

These are the first major construction projects funded by the Building Excellence V (BEX V) capital levy, which was approved by voters in February 2019. The classroom addition projects were also funded by grants from the state of Washington.

Elementary School Replacements

Demolition and site-clearing activities at Kimball and Viewlands are nearing completion. The construction team have started laying out the new building with concrete work for the new school scheduled to begin next month. School opened for both schools at interim locations — Kimball at Van Asselt School and Viewlands at John Marshall School.

At James Baldwin, changes were made over the summer in preparation for students and staff to remain on site during construction. Geothermal well installation and site grading took place on the existing field where the new school building is now being constructed. Once the school moves to the new building for the 2023-24 school year, the old building will be demolished, and new play areas will be constructed.

Lincoln Phase II

Prior to opening Lincoln High School in 2019, the historic buildings on the west side of the campus were modernized. Now phase II has begun on the east side of the Lincoln campus. This project involves seismic improvements to the gymnasium and Performing Arts Center buildings and includes adding Career and Technical Education (CTE) classrooms.

School Expansions

West Seattle Elementary School is also temporarily occupying an interim site, Schmitz Park School, while construction activities are occurring at their school building. Construction has started on the 12-classroom addition and a redesigned secure entrance. The project plans a new entry canopy, relocating the library and administration areas, and modernization of the existing classrooms. Mechanical system upgrades and a minor modernization to the existing school building will also be implemented.

The addition at Leschi Elementary School includes four new classrooms to help relieve crowding. Expanding the school will allow preschool to return.

A new two-story addition on the north side Madison Middle School will also help relieve crowding. It includes six new general classrooms, two new science classrooms, and learning support spaces.

All three addition projects are scheduled to be complete for the 2022-23 school year.

More

You can learn more about these projects on the construction projects pages. Updates and photos of ongoing construction activities are posted each month.

You may also be interested in

a crane is installing steel framing for a large building

Capital Levy Report to the Community

Your Tax Dollars at Work: Capital levies are the main source of funding for school construction and building improvements, as well as technology!…
a group of young men stand in front of a brick building holding up shirts

Youth in Construction Brings Students to Montlake Project

Site Visit Introduces High School Students to Construction Careers Students from the Kingmakers program at Franklin High School and a part of the WHOLE Mentoring program from Ingraham High School visited the construction project underway at Montlake Elementary School on April 4 with the help of Skanska’s Youth in Construction…

No Landmark Status for Existing Mercer International Middle School

No Landmark Status for Existing Mercer International Middle School On Wednesday May 19, 2021, the City of Seattle voted against designating the current Mercer International Middle School building as a landmarked structure, allowing for the construction of a new school building. Seattle voters approved the Building Excellence V Capital Levy…