    Timeline

    • Predesign phase complete.
    • Schematic design phase complete.
    • Design development phase complete.
    • Construction documents and permitting phase in progress.
    • Bid and award contracts phase begins Winter 2021.
    • Construction phase begins Spring 2021.
    • Addition opens Fall 2022.

    Current Project Phase: Construction Documents and Permitting 

    Recent Progress

    Progress updates are posted for the previous month the week after the monthly BEX and BTA Capital Levies Oversight Committee meetings. These meetings typically take place on the first Friday of each month.

    March 2021

    • Determination of Non Significance (DNS) issued
      • Appeal period ended March 30
    • Submitted portable relocation permit

    Virtual Community Meeting

    The project management and design team held a virtual community meeting on Thursday, Nov. 12, 2020, to provide updates on the project.  

    See the PDF of the presentationadobe PDF icon

    Project Overview

    A 12,500-square-foot classroom addition will be constructed at Madison Middle School to accommodate enrollment growth.

    Project Manager: Vince Gonzales

    School Design: Studio Meng Strazzara

    Project Budget: $10.5M

    Funding Source: Funded by State of Washington Distressed Schools Grant

    School Design Advisory Team

    The School Design Advisory Team (SDAT) met virtually because of the pandemic. Information about SDAT and meeting minutes are posted.

     

    Contact Us

    Please send us your questions or comments with the form below.

    photo of a multi-story brick building

    James Madison Middle School

    3429 45th Ave SW
    Seattle, WA 98116

    School profile

    School website

    Construction Projects and Capital Levies News