    Updates on Major Construction Projects
    Posted on 05/30/2019
    Overall site photo of the Queen Anne Elementary addition construction

    Updates on Major Capital Levy-Funded Construction Projects

    Construction work funded by voter-approved capital levies continues at Queen Anne Elementary, Lincoln High School, Ingraham High School, and Magnolia Elementary. Capital levies are the primary source of funds for school construction and renovations. Current projects are funded by the Building Excellence IV (BEX IV) Capital Levy, approved by voters in 2013, and by the Buildings, Technology, and Academics IV (BTA IV) Capital Levy, approved by voters in 2016.

    Highlights

    photo of a classroom under construction with ceiling grid showing

    photo of reception area of office under construction

    Queen Anne Elementary addition (BEX IV): The classroom addition now has permanent power, and the roof is nearly complete. Work underway includes painting, ceramic tile, and ceiling grid installation. The new construction also includes administration offices, and a new gymnasium. The ceiling and duct work in the gym have been painted, and the office area is nearly ready for paint.

     

    photo of stairway with wrought iron railings

    photo of concrete walkways outside a brick building

    photo of a large two story room under construction with windows and a forum type stairway

    Lincoln High School modernization (BEX IV): The school now has concrete walkways in the courtyard area, and framing is underway for the new entrance. Work continues on wallboard installation and finishes such as paint, casework, and flooring. Guardrails are being fabricated for the historic stairways. Work continues in the commons and kitchen.

     

    photo of building exterior with metal panels being installed

    photo of large concrete stairway in a large room that is under construction

    Ingraham High School addition (BTA IV): Roofing, window installation, and masonry work are nearly complete. Work to install metal siding and flashing started. All classrooms are painted, and ceiling grids are being installed. 

     

    Magnolia Elementary addition and modernization (BTA IV): see story.